New Hospital Site Abuzz in Activity

Posted 17 June 2014 1:14 PM by TCAuthor3

By Jeff Maciejewski, Project Engineer, Boldt

The job site at the new ThedaCare Medical Center-Shawano has become more active over the past month. Additional crews are now on site as construction progresses into a new phase. Concrete pours for second floor have been ongoing and should be complete by the end of the month.

Once the plumbers and electricians are done installing their underground utilities, the concrete pours on first floor will begin. Roofing crews have also started in the last month. About half of the roof for the new addition has been installed.  With concrete and roofing complete in certain areas, crews have started laying out the walls for the interior.  

Over the next month, the remaining concrete floor slabs will be poured, masonry brick and stone work will continue, interior walls will start to be framed up, and the mechanical, electrical and plumbing contractors will start their rough-ins for the interior build out.