Paint, Ceilings, Flooring, and Plumbing in the Works

Posted 18 March 2015 11:50 AM by TCAuthor3

By Zach Whitney, Project Manager, Boldt

Construction work is progressing quickly within the new ThedaCare Medical Center-Shawano.  Casework is being delivered weekly as crews work throughout the building.  Twelve semi-trailer loads are scheduled to complete the delivery of casework. 

In many areas on the second level ceiling grid, finished flooring and plumbing fixtures have been installed.  On the first level painting is almost complete as drywall finishing activities were completed earlier this month.  Installation of finishes will soon commence on the first level. 

With warmer spring temperatures in the near future, site work is scheduled with various contractors for the installation of concrete sidewalks, curbs, asphalt and landscaping.